1. |
A can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone? |
A. | 8 days |
B. | 12 days |
C. | 10 days |
D. | 16 days |
Answer» C. 10 days | |