1.

A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?

A.
B. <table><tr><td rowspan="2">42</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>3</center></td><td rowspan="2">days</td></tr><td align="center">4</td></table>
C. <table><tr><td rowspan="2">27</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><td align="center">7</td></table>
D. <table><tr><td rowspan="2">17</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><td align="center">7</td></table>
E. 70 days
Answer» D. <table><tr><td rowspan="2">17</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><td align="center">7</td></table>