

MCQOPTIONS
Saved Bookmarks
1. |
A can do a piece of work in 24 days. If B is 60% more efficient than A, then B can complete the work in - |
A. | 17 days |
B. | 18 days |
C. | 15 days |
D. | 12 days |
Answer» D. 12 days | |