A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ? |
| A. | ${\text{6}}\frac{3}{5}$$ |
| B. | ${\text{8}}\frac{1}{2}$$ |
| C. | ${\text{10}}\frac{1}{5}$$ |
| D. | ${\text{13}}\frac{1}{2}$$ |
| Answer» D. ${\text{13}}\frac{1}{2}$$ | |