A can do a piece of work in 12 days. He worked for 15 days and then B completed the remaining work in 10 days. Both of them together will finish it in. |
A. | 12 1/2 days |
B. | 25 days |
C. | 6 days |
D. | 12 days |
Answer» B. 25 days | |