1. |
A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ? |
A. | 6 days |
B. | 8 days |
C. | 10 days |
D. | 13 days |
Answer» E. | |