| 1. |
A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B and C finish it, working all together? |
| A. | 6 days |
| B. | 5Â 1/4 days |
| C. | 4Â 4/11 days |
| D. | 4 days |
| Answer» E. | |