1. |
A can do a piece of work in 10 days and B can do the same work in 12 days. A and B worked together for 2 days. How many more days are required to complete the remaining work if they work together? |
A. | 2(2/11)days |
B. | 3(3/11)days |
C. | 3(5/11)days |
D. | 6(3/11)days |
Answer» D. 6(3/11)days | |