A can do a job in 10 days. Due to problematic relationship with B, his efficiency reduces to 60% and both can finish the job in 10 days. In how many days can B complete the whole job? |
A. | 15 |
B. | 25 |
C. | 30 |
D. | 35 |
Answer» C. 30 | |