A can do a job in 10 days and B can do the same job in 15 days. They start working together, but B leaves after 5 days. How many more days A want to finish the work ? |
A. | 2 days |
B. | <table><tr><td rowspan="2">1</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>2</center></td><td rowspan="2">days</td></tr><tr><td style="text-align: center;">3</td></tr></table> |
C. | 3 days |
D. | <table><tr><td rowspan="2">2</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>2</center></td><td rowspan="2">days</td></tr><tr><td style="text-align: center;">3</td></tr></table> |
Answer» C. 3 days | |