A can do a certain job in 12 days and B is 60%more efficient than A. The B can do the same piece of work in ?

A. ${\text{8 days}}$$
B. ${\text{7}}\frac{1}{2}{\text{ days}}$$
C. ${\text{6}}\frac{1}{4}{\text{ days}}$$
D. ${\text{6 days}}$$
Answer» C. ${\text{6}}\frac{1}{4}{\text{ days}}$$