1. |
A can do 7/8 of work in 28 days, B can do 5/6 of the same work in 20 days. The number of days they will take to complete if they do it together is |
A. | <table><tr><td rowspan="2">15</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>3</center></td><td rowspan="2">days </td></tr><td align="center">7</td></table> |
B. | <table><tr><td rowspan="2">17</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>3</center></td><td rowspan="2">days </td></tr><td align="center">5</td></table> |
C. | <table><tr><td rowspan="2">14</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>5</center></td><td rowspan="2">days </td></tr><td align="center">7</td></table> |
D. | <table><tr><td rowspan="2">13</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>5</center></td><td rowspan="2">days </td></tr><td align="center">7</td></table> |
Answer» E. | |