1. |
A can do 1/2 of a piece of work in 5 days, B can do 3/5 of the same work in 9 days and C can do 2/3 of that work in 8 days. In how many days can three of them together do the work ? |
A. | 3 days |
B. | 5 days |
C. | <table><tr><td rowspan="2">4</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days </td></tr><td align="center">2</td></table> |
D. | 4 days |
Answer» E. | |