1.

A can complete one-third of a work in 5 days and B can complete 40% of the work in 10 days. In how many days both A and B together can complete the work?

A. \(\frac{81}{7}\) days
B. \(\frac{29}{4}\) days
C. \(\frac{75}{8}\) days
D. 10 days
Answer» D. 10 days