A can complete a work in 8 days working 10 hours in a day and B can do the same in 12 days, working 8 hours a day. If both are working together, working 6 hours a day, in how many days can they complete the work?

A. \(7\frac{3}{11}\)
B. \(7\frac{1}{11}\)
C. \(7\frac{9}{11}\)
D. \(7\frac{5}{11}\)
Answer» B. \(7\frac{1}{11}\)