| 1. |
A can complete a work in 12 days and B can complete in 8 days. A works for 8 hours every day while B works for 10 hours every day. If A and B together start working 8 hours per day, in how many days will they complete the work? |
| A. | 8 days |
| B. | 60/11 days |
| C. | 39/12 days |
| D. | 15/8 days |
| Answer» C. 39/12 days | |