| 1. |
A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself? |
| A. | 36 |
| B. | 32 |
| C. | 40 |
| D. | 30 |
| Answer» D. 30 | |