MCQOPTIONS
Saved Bookmarks
1. |
A can complete a piece of work in 40 days and B is 30% more efficient than A. In how many days will the work be completed, if both are working together? |
A. | 600/23 |
B. | 400/23 |
C. | 500/23 |
D. | 380/23 |
E. | None of these |
Answer» C. 500/23 | |