 A can complete a job in 9 days, B in 10 days and C in 15 days. B and C start the work together and are forced to leave after 2 days. The time taken to complete the remaining work is

A. 15 days
B. 22 days
C. 6 days
D. 19 days
Answer» D. 19 days