1.

A can complete a job in 9 days, B in 10 days and C in 15 days. B and C start the work and are forced to leave after 2 days. The time taken to complete the remaining work is ?

A. 6 days
B. 9 days
C. 10 days
D. 13 days
Answer» B. 9 days


Discussion

No Comment Found