A can complete 9/10 part of a work in 31 days. After that, with the help of B he can complete the remaining work in 4 days. In how many days will A and B together can complete that work ? |
| A. | 36 |
| B. | 40 |
| C. | 42 |
| D. | 38 |
| Answer» C. 42 | |