1. |
A bearing manufacturing company supplies 10,000 bearings per day to an automobile company. The company finds it can produce 25,000 per day when the production run starts. Holding the stock for a year at Rs. 2 per unit setup cost of a production run is Rs. 1,800. The economic lot size for each production run is: |
A. | 265430 |
B. | 104642 |
C. | 124631 |
D. | 350765 |
Answer» C. 124631 | |