| 1. |
A & B together finish a job in 24 days, while A, B & C together can finish the same job in 8 days. C alone will finish the job in |
| A. | 12 days |
| B. | 14 days |
| C. | 16 days |
| D. | 24 days |
| Answer» B. 14 days | |