A, B and C, working alone can do a piece of work in 12, 24 and 36 days respectively. They work together and get Rs. 3850 for completing the work. What is the difference in shares of B and C? |
A. | Rs. 1050 |
B. | Rs. 350 |
C. | Rs. 700 |
D. | Rs. 1400 |
Answer» C. Rs. 700 | |