A, B and C contract to do a work for 4200. A can do the work in 6 days, B in 10 days and C in 12 days. If they work together to do die work, what is the share of each?
A B C

A. 1000 1200 2000
B. 1100 1100 2000
C. 1000 2000 1200
D. 2000 1200 1000
Answer» E.