| 1. |
A, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining task is:_x005F_x000D_ |
| A. | 16.5 days |
| B. | 13 days |
| C. | 10 days |
| D. | 12.5 days |
| Answer» B. 13 days | |