1. |
A, B and C can individually complete a task in 20 days, 16 days, and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining task is: |
A. | 13 days |
B. | \(16\frac{1}{2}\) days |
C. | 10 days |
D. | \(12\frac{1}{2}\) days |
Answer» C. 10 days | |