A, B and C can do apiece of work in 36 days, 54 days and 108 days, respectively. They started the work together but a left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work? |
A. | 29 |
B. | 33 |
C. | 30 |
D. | 31 |
Answer» B. 33 | |