MCQOPTIONS
Saved Bookmarks
| 1. |
A, B and C can complete a work in 10, 15 and 20 days respectively. A and B start it together. B is replaced by C after 2 days. A leave it after one more day. In how many days work was completed? |
| A. | 13 |
| B. | (13 {1 over 13 } ) |
| C. | (18 {4 over 3 } ) |
| D. | 18 |
| Answer» C. (18 {4 over 3 } ) | |