A, B and C can complete a work in 10, 12 and 15 days respectively. All three of them starts together but after 2 days A leaves the job and B left the job 3Â days before the work was completed. C completed the remaining work alone. In how many days was the total work completed? |
| A. | 5 |
| B. | 6 |
| C. | 7 |
| D. | 8 |
| Answer» D. 8 | |