1. |
A, B and C can complete a work in 10, 12 and 15 days respectively. All three of them starts together but after 2 days A leaves the job and B left the job 3 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed? |
A. | 5 |
B. | 6 |
C. | 7 |
D. | 8 |
Answer» D. 8 | |