A, B and C can complete a task together in 8 days. A and B would need 16 days if only the two of them worked, while A and C would take 12 days if only the two of them worked. If A worked alone, how many days would A take to compete the task? |
A. | 30 |
B. | 48 |
C. | 60 |
D. | 45 |
Answer» C. 60 | |