1.

A and B working together can complete a piece of work in 12 days. B and C working together can complete the same work in 16 days. A worked at it for 5 days and B worked at it for 7 days. C finished the remaining work in 13 days. How many days would C alone take to complete it?

A. 32
B. 24
C. 10
D. 40
Answer» C. 10