                                    A and B working separately can complete a piece of work in 9 and 12 days respectively. If they work alternatively starting from A in how many days will the work be completed? | 
                            
| A. | 10.25 days | 
| B. | 11.5 days | 
| C. | 12.75 days | 
| D. | 9 days | 
| Answer» B. 11.5 days | |