1.

A and B working separately can complete a piece of work in 9 and 12 days respectively. If they work alternatively starting from A in how many days will the work be completed?

A. 10.25 days
B. 11.5 days
C. 12.75 days
D. 9 days
Answer» B. 11.5 days