A and B working saperately can do a piece of work in 12 and 18 hours respectively. If they work for 6 hour alternately with B beginning, in how many hours will the work be completed? |
A. | 9 hours |
B. | 15 hours |
C. | 13 ½ hours |
D. | 12 ½ hours |
Answer» C. 13 ½ hours | |