| 1. |
A and B undertaken to do a piece of work for 1200. A alone can do it in 8 days, while B can do it in 6 days. With the help of C, they complete it in 3 days. Find C's share. |
| A. | 450 |
| B. | 300 |
| C. | 150 |
| D. | 100 |
| Answer» D. 100 | |