1. |
A and B together complete a piece of work in T days. If A alone completes the work in T + 3 days and B alone completes the piece of work in T + 12 days, what is T ? |
A. | days |
B. | days |
C. | 2 days |
D. | annot be determined |
E. | one of these |
Answer» F. | |