A and B together can finish a work in 15 days. A and C take 2 days more to complete the same work than that of B and C. A, B and C together complete the work in 8 days. In how many days will A finish it separately? |
A. | 40 days |
B. | 24 days |
C. | <table><tr><td rowspan="2">17</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><td align="center">7</td></table> |
D. | 20 days |
Answer» B. 24 days | |