A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how days would it have taken it have taken B to do the work by herself? |
A. | 1.5 |
B. | 1.8 |
C. | 2 |
D. | 2.2 |
Answer» D. 2.2 | |