A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest work in 14 days. A alone can complete the work in _____. |
A. | 24 days |
B. | 22 days |
C. | 20 days |
D. | 18 days |
Answer» B. 22 days | |