A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, where upon A leaves. B continues for 2 more days, and then he leaves too. C now starts working, and finishes the job. How many days did C require ? |
A. | 5 |
B. | 8 |
C. | 3 |
D. | 4 |
Answer» E. | |