| 1. |
A and B can together do a piece of work in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is |
| A. | 18 days |
| B. | 24 days |
| C. | 9 days |
| D. | 12 days |
| Answer» B. 24 days | |