A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is: |
A. | 15 days |
B. | 18 days |
C. | 12 days |
D. | 10 days |
Answer» D. 10 days | |