 A and B can do a work in 12 days, B and C in 30 days and C and A in 36 days. In how many days will the work be completed, if all three of them work together?

A. 160/11 days
B. 125/14 days
C. 180/13 days
D. 120/11 days
Answer» D. 120/11 days