1. |
A and B can do a work in 12 days, B and C in 30 days and C and A in 36 days. In how many days will the work be completed, if all three of them work together? |
A. | 160/11 days |
B. | 125/14 days |
C. | 180/13 days |
D. | 120/11 days |
Answer» D. 120/11 days | |