A and B can do a work in 12 days, B and C can do the same work in 15 days, and C and A can do the same work in 20 days. A, B and C will complete the work together in: |
A. | 20 days |
B. | 28 days |
C. | 12 days |
D. | 10 days |
E. | None of these |
Answer» E. None of these | |