A and B can do a piece of work in 4 days, while C and D can do the same work in 12 days. In how many days will A, B, C and D do it together? |
| A. | 12 days |
| B. | 4 days |
| C. | 3 days |
| D. | 2 days |
| Answer» D. 2 days | |