A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work? |
| A. | 18 days |
| B. | 24 days |
| C. | 30 days |
| D. | 36 days |
| Answer» B. 24 days | |