'A' and ' B ' can do a piece of work in 25 days and 30 days respectively. Both start the work together but 'A' leaves the work 8 days before its completion. Find the time in which the work is finished |
A. | 18 days |
B. | 21 days |
C. | 25 days |
D. | 27 days |
Answer» B. 21 days | |