A and B can do a piece of work in 12 days while B and C can do in 24 days, and C and A in 20 days. They all work together on it for 10 days and then B and C leave. How many days more A will take to complete the work? |
A. | \(3\frac{2}{3}\) days |
B. | \(3\frac{1}{3}\) days |
C. | \(4\frac{5}{{11}}\) days |
D. | \(2\frac{8}{{11}}\) days |
Answer» E. | |